HELP. Building a maisonette in phases [15]
tape lift [2]
Efficient and Affordable Clearing agent at Msa Por... [7]
100% solar powered maisonette possible? [47]
Olymp Trade's trading terms [9]
1/4 plot for sale in Katani next to the road [1]
Cost of architectural plans in Kenya [24]
A guide to imporing cars from Japan [323]
Ubapesa [101]
Looking for a Puppy. [17]
shylock [11]
Car hire in Nairobi [18]
Nairobi County Parking Rates [2]
Easy and Fast Shipping of goods from U.S.A to Keny... [5]
Terrible, terrible walling! [18]
 
Forum Jump








Welcome Guest Search | Active Topics | Log In | Register

HELP. Building a maisonette in phases
amorphous
#1 Posted : Wednesday, May 15, 2019 5:59:42 AM
Rank: Hello


Joined: 5/15/2019
Posts: 5
Location: planet earth
what to do about the staircase area once suspended slab is poured? Sad It is open to the skies kabisa and thus a huge void in the slab
Si tutanyeshewa kunyeshwo?
Planning to finish ground floor and move in but staircase area ndio chinda.
Thanks in advance Wazua.

Queen
#2 Posted : Wednesday, May 15, 2019 8:18:53 AM
Rank: New-farer


Joined: 11/21/2018
Posts: 79
Location: Britain
You may have to do a false roof not just above the staircase void but the entire first floor slab. The reason being a concrete slab is permeable so you should otherwise expect water leakage through the slab. Doing a maisonette in phases can be quite expensive.

A better mode of construction would entail doing the entire first floor walling including the roof. The finishes on first floor can follow later as you chill on the ground floor.
obiero
#3 Posted : Wednesday, May 15, 2019 8:51:43 AM
Rank: Elder


Joined: 6/23/2009
Posts: 11,458
Location: nairobi
Queen wrote:
You may have to do a false roof not just above the staircase void but the entire first floor slab. The reason being a concrete slab is permeable so you should otherwise expect water leakage through the slab. Doing a maisonette in phases can be quite expensive.

A better mode of construction would entail doing the entire first floor walling including the roof. The finishes on first floor can follow later as you chill on the ground floor.

This is the best guidance that I have seen in wazua in 2019
COOP 5,500; KCB 3,700; KQ 221,100
amorphous
#4 Posted : Wednesday, May 15, 2019 10:52:59 AM
Rank: Hello


Joined: 5/15/2019
Posts: 5
Location: planet earth
Queen wrote:
You may have to do a false roof not just above the staircase void but the entire first floor slab. The reason being a concrete slab is permeable so you should otherwise expect water leakage through the slab. Doing a maisonette in phases can be quite expensive.

A better mode of construction would entail doing the entire first floor walling including the roof. The finishes on first floor can follow later as you chill on the ground floor.


Excellent observation my sister. But shida ni pesa. I don't have enough to even fika the ring beam let alone the roof!
I was thinking just build a mini mabati roof over the staircase area and then move in. I never knew concrete slabs are permeable? Aren't some roof tiles also made of concrete? I would think a think suspended slab is virtually impermeable, and the water that seeps in and is retained is actually good for long term curing of the slab? Asanteni for the feedback.
Queen
#5 Posted : Thursday, May 16, 2019 9:04:40 AM
Rank: New-farer


Joined: 11/21/2018
Posts: 79
Location: Britain
Del.

Queen
#6 Posted : Thursday, May 16, 2019 11:50:33 AM
Rank: New-farer


Joined: 11/21/2018
Posts: 79
Location: Britain
amorphous wrote:
Queen wrote:
You may have to do a false roof not just above the staircase void but the entire first floor slab. The reason being a concrete slab is permeable so you should otherwise expect water leakage through the slab. Doing a maisonette in phases can be quite expensive.

A better mode of construction would entail doing the entire first floor walling including the roof. The finishes on first floor can follow later as you chill on the ground floor.


Excellent observation my sister. But shida ni pesa. I don't have enough to even fika the ring beam let alone the roof!
I was thinking just build a mini mabati roof over the staircase area and then move in. I never knew concrete slabs are permeable? Aren't some roof tiles also made of concrete? I would think a think suspended slab is virtually impermeable, and the water that seeps in and is retained is actually good for long term curing of the slab? Asanteni for the feedback.


There is no aspect of construction which is cheaper than doing masonry walling. If you do not have cash in the interim to lay roof tiles, you may roof with gauge 32 mabatis which shall double up as underlays for the tiles at a later date when your financial position improves.
githundi
#7 Posted : Saturday, May 18, 2019 9:46:40 AM
Rank: Veteran


Joined: 11/19/2010
Posts: 1,290
Location: nairobi metropolitan
amorphous wrote:
Queen wrote:
You may have to do a false roof not just above the staircase void but the entire first floor slab. The reason being a concrete slab is permeable so you should otherwise expect water leakage through the slab. Doing a maisonette in phases can be quite expensive.

A better mode of construction would entail doing the entire first floor walling including the roof. The finishes on first floor can follow later as you chill on the ground floor.


Excellent observation my sister. But shida ni pesa. I don't have enough to even fika the ring beam let alone the roof!
I was thinking just build a mini mabati roof over the staircase area and then move in. I never knew concrete slabs are permeable? Aren't some roof tiles also made of concrete? I would think a think suspended slab is virtually impermeable, and the water that seeps in and is retained is actually good for long term curing of the slab? Asanteni for the feedback.

Boss, It is doable, weka floor on the concrete roof the same way it done on flats. I have had it for almost 2 years and no leakage. Also put a temporary mabati roof on the starecase and move in.
Good luck!!
Democracy does not belong to the dead
amorphous
#8 Posted : Saturday, May 18, 2019 10:22:29 AM
Rank: Hello


Joined: 5/15/2019
Posts: 5
Location: planet earth
Queen wrote:
amorphous wrote:
Queen wrote:
You may have to do a false roof not just above the staircase void but the entire first floor slab. The reason being a concrete slab is permeable so you should otherwise expect water leakage through the slab. Doing a maisonette in phases can be quite expensive.

A better mode of construction would entail doing the entire first floor walling including the roof. The finishes on first floor can follow later as you chill on the ground floor.


Excellent observation my sister. But shida ni pesa. I don't have enough to even fika the ring beam let alone the roof!
I was thinking just build a mini mabati roof over the staircase area and then move in. I never knew concrete slabs are permeable? Aren't some roof tiles also made of concrete? I would think a think suspended slab is virtually impermeable, and the water that seeps in and is retained is actually good for long term curing of the slab? Asanteni for the feedback.


There is no aspect of construction which is cheaper than doing masonry walling. If you do not have cash in the interim to lay roof tiles, you may roof with gauge 32 mabatis which shall double up as underlays for the tiles at a later date when your financial position improves.


Queen yes I agree with you on walling but you forgot the small matter of roofing mbaos and roofing labour! Hizi mbili sio mchezo. Ring beam pia will eat money.
amorphous
#9 Posted : Saturday, May 18, 2019 11:22:32 AM
Rank: Hello


Joined: 5/15/2019
Posts: 5
Location: planet earth
githundi wrote:
amorphous wrote:
Queen wrote:
You may have to do a false roof not just above the staircase void but the entire first floor slab. The reason being a concrete slab is permeable so you should otherwise expect water leakage through the slab. Doing a maisonette in phases can be quite expensive.

A better mode of construction would entail doing the entire first floor walling including the roof. The finishes on first floor can follow later as you chill on the ground floor.


Excellent observation my sister. But shida ni pesa. I don't have enough to even fika the ring beam let alone the roof!
I was thinking just build a mini mabati roof over the staircase area and then move in. I never knew concrete slabs are permeable? Aren't some roof tiles also made of concrete? I would think a think suspended slab is virtually impermeable, and the water that seeps in and is retained is actually good for long term curing of the slab? Asanteni for the feedback.

Boss, It is doable, weka floor on the concrete roof the same way it done on flats. I have had it for almost 2 years and no leakage. Also put a temporary mabati roof on the starecase and move in.
Good luck!!
Thanks boss,
I've settled on this course of action. It's been raining on and off and I see no leaks anywhere except water on staircase. Nitaweka mabati niingie jameni. Rent is eating me alive!! Thanks for the encouragement.
newfarer
#10 Posted : Saturday, May 18, 2019 11:37:26 AM
Rank: Elder


Joined: 3/19/2010
Posts: 3,143
Location: Uganda
obiero wrote:
Queen wrote:
You may have to do a false roof not just above the staircase void but the entire first floor slab. The reason being a concrete slab is permeable so you should otherwise expect water leakage through the slab. Doing a maisonette in phases can be quite expensive.

A better mode of construction would entail doing the entire first floor walling including the roof. The finishes on first floor can follow later as you chill on the ground floor.

This is the best guidance that I have seen in wazua in 2019

I lived in a house with slab roof for 4 years with zero leakage.just ensure no water stagnates on the slab
punda amecheka
limanika
#11 Posted : Saturday, May 18, 2019 3:56:33 PM
Rank: Veteran


Joined: 9/21/2011
Posts: 1,911
newfarer wrote:
obiero wrote:
Queen wrote:
You may have to do a false roof not just above the staircase void but the entire first floor slab. The reason being a concrete slab is permeable so you should otherwise expect water leakage through the slab. Doing a maisonette in phases can be quite expensive.

A better mode of construction would entail doing the entire first floor walling including the roof. The finishes on first floor can follow later as you chill on the ground floor.

This is the best guidance that I have seen in wazua in 2019

I lived in a house with slab roof for 4 years with zero leakage.just ensure no water stagnates on the slab
limanika
#12 Posted : Saturday, May 18, 2019 3:58:53 PM
Rank: Veteran


Joined: 9/21/2011
Posts: 1,911
...Then for the staircase well area only build up perimeter temporary masonry walling and do the temporary roof at high level.
amorphous
#13 Posted : Tuesday, May 21, 2019 7:15:09 AM
Rank: Hello


Joined: 5/15/2019
Posts: 5
Location: planet earth
limanika wrote:
...Then for the staircase well area only build up perimeter temporary masonry walling and do the temporary roof at high level.


Not a bad idea. This will also allow me (and the fundis) to access the first floor in case i need to inspect the solar water heater and water tank that will be temporarily placed there. The fundis will be able to continue building once i save up the money.
limanika
#14 Posted : Tuesday, May 21, 2019 5:59:41 PM
Rank: Veteran


Joined: 9/21/2011
Posts: 1,911
amorphous wrote:
limanika wrote:
...Then for the staircase well area only build up perimeter temporary masonry walling and do the temporary roof at high level.


Not a bad idea. This will also allow me (and the fundis) to access the first floor in case i need to inspect the solar water heater and water tank that will be temporarily placed there. The fundis will be able to continue building once i save up the money.

Exactly. The fundis should access via an external ladder though
Mkimwa
#15 Posted : Tuesday, May 21, 2019 6:52:17 PM
Rank: Member


Joined: 10/26/2008
Posts: 369
Your staircase has no steps on it, just 2 landings..

Or are those to be introduced later?

amorphous wrote:
what to do about the staircase area once suspended slab is poured? Sad It is open to the skies kabisa and thus a huge void in the slab
Si tutanyeshewa kunyeshwo?
Planning to finish ground floor and move in but staircase area ndio chinda.
Thanks in advance Wazua.


Users browsing this topic
Guest (2)
Forum Jump  
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.

Home | . .. Investor | .. . Groups | .. . SME | . . . Market | .. . Club SK | . ..... About Wazua | . .. Search | . ..Sitemap | . ..Support | . ..Disclaimer | . ..Privacy Policy | . ..Terms of Use | . .. Contact Us
Copyright © 2019 Wazua.co.ke. All Rights Reserved.